Directions:

Obtain project details by selecting the desired project on the map, or review a list of unmapped projects from the link above.


Lee's Summit, MO

Arbores Pump Station

Last Updated

08/12/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

May 09, 2012 - Nov 09, 2012

Project Status

In Design

Projected Funding:

$459,000

Project Description:

This project involves removal of the Arbores Pump Station and installation of approximately 2,000 feet of gravity line.

Project Rationale:

The pump station is 25 years old and requires significant maintenance and rehabilitation if use continues. Replacement with a gravity line will eliminate the need for maintenance and rehabilitation as well as ongoing operating costs to run a pump station.

Current Project Status:


Bailey Road, Route 291 to Hamblen Rd

Last Updated

07/27/2011

Project Manager(s):

Scott Ward
816-969-1849

Estimated Construction Dates:

Aug 01, 2011 - Dec 31, 2012

Project Status

In Design

Projected Funding:

$8,389,000

Project Description:

This project is one of six in the Lee's Summit Thoroughfare Master Plan. Funding for this project comes from the extension of the 1/2 cent sales tax (for Transportation Improvements) passed by voters in the spring of 2007. The project will construct a new roadway from M-291 east to the intersection of Hamblen Road and Bailey Road. A significant part of the project will be the design and construction of a bridge over the Union Pacific Railroad.

Project Rationale:

Current Project Status:

Design work is nearing completion. Since the property acquisition and construction agreement with the Union Pacific Railroad will not be completed in time to meet the proposed construction start date, the work will be split into two construction projects. The west portion, from M-291 to a point approximately 1000 feet to the east, will be constructed this summer. Pfizer's entrance will be relocated, and the improvements will allow the development of the adjoining property. The remaining portion, including the bridge over the UPRR, will be built as soon as an agreement is reached with the Union Pacific Railroad.


Bayview Drive Water- Channel Dr to Shore Line Dr

Last Updated

08/15/2011

Project Manager(s):

Kevin York
816-969-1818

Estimated Construction Dates:

Feb 01, 2011 - Dec 31, 2013

Project Status

In Design

Projected Funding:

$656,000

Project Description:

Relocation of approximately 2,300 linear feet of 6-inch and 8-inch water mains and service connections along Bayview Drive from Channel Dr to Shore Line Drive. Plans include relocating the line along the existing roadway due to the numerous obstructions along the existing alignment.

Project Rationale:

The existing line is deep and located under retaining walls, sidewalks and landscaping features, which results in high maintenance costs when repairs are needed. The main has experienced several breaks.

Current Project Status:

This project was scheduled for construction during the summer of 2011. This project has since been combined with the Water Main Rehab-FY 2011 and the Water Main Rehab-FY 2012 projects. The estimated construction schedule includes the combination of all three projects in the 2011-2015 Capital Improvement Program for Water Utilities projects. Estimated start and completion dates will vary between each project location as work proceeds.


Blackwell Interchange at 50 HWY

Last Updated

11/17/2011

Project Manager(s):

Michael Park
816-969-1820

Estimated Construction Dates:

Apr 01, 2014 -

Project Status

In Design

Projected Funding:

$23,000,000

Project Description:

Extension of Blackwell Road across 50 Highway, having a diamond interchange. Construction of Blue Parkway to Blackwell Road and Oldham Parkway to Smart Road, with an intersection at Blackwell Road. This project will be fully funded by the East 50 HWY TIF and managed by the City of Lee's Summit. MoDOT, City of Lake Lottawanna and Jackson County are supporting agencies with property interests and/or ownership.

Project Rationale:

Traffic conditions at the interchange of Todd George Parkway and 50 Highway will not accomodate the immediate and projected growth of surrounding development. Improvements to Todd George Parkway interchange are planned, but cannot mitigate the traffic congestion without alternate access to 50 Highway in eastern Lee's Summit. Blackwell interchange has been planned for over 40 years. Blackwell interchange will relieve some of the congestion at Todd George Parkway and surrounding streets, provide better access to eastern Lee's Summit, minimize the impact of travel during construction at Todd George Interchange, encourage economic development in the newly annexed property and meet the City's long range traffic demand.

Current Project Status:

Design is approximately 98% complete. The interchange has been designed with roundabout traffic control where the ramps intersect with Blackwell Road and at the intersection of Blackwell Road and Blue Parkway/Shenandoah Drive. All permits and enviornmental clearances have been approved. Acquisition of right-of-way, utility relocation and construction will be deferred until TIF funds are available to cover associated project costs. Such funding is contingent on development activity within the TIF Area.


CC Watershed - CC-16, CC- 20 Private I/I Rehab

Last Updated

08/12/2011

Project Manager(s):

Kevin York
816-969-1818

Estimated Construction Dates:

Oct 01, 2010 -

Project Status

In Construction

Projected Funding:

$584,000

Project Description:

This sanitary sewer improvement project consists of completing the private I/I rehabiliation work identified in the Sewer System Evaluation Survey(SSES) in the identified sub-watersheds CC-16 and CC-20. These improvements consist of removal of ground water infiltration and inflow from home drain systems.

Project Rationale:

This project will serve existing customers by reducing I/I from these sources which will alleviate sanitary sewer overflows and backups in homes.

Current Project Status:


CC Watershed - CC-17, CC- 21 Private I/I Rehab

Last Updated

08/12/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

Jul 01, 2014 - Jul 01, 2016

Project Status

Future

Projected Funding:

$1,959,000

Project Description:

This sanitary sewer improvement project consists of completing the private I/I rehabiliation work identified in the Sewer System Evaluation Survey (SSES) in the identified sub-watersheds CC-17 and CC-21. These improvements consist of removal of ground water infiltration and inflow from home drain systems.

Project Rationale:

This project will serve existing customers by reducing I/I from these sources which will alleviate sanitary sewer overflows and backups in homes.

Current Project Status:


Cedar Creek Interceptor Improvements 2-2

Last Updated

08/15/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

Jul 02, 2012 - Dec 02, 2012

Project Status

In Design

Projected Funding:

$2,645,000

Project Description:

This sanitary sewer improvement project consists of the construction of approximately 9300 LF of sanitary sewer lines ranging in pipe size from 36-inches to 48-inches in diameter on the upper segments of Cedar Creek interceptor.

Project Rationale:

The existing sanitary sewer lines do not have capacity to convey the predicted wet-weather flows nor meet the future needs of development in the watershed. A federal grant was obtained through economic development contacts which will pay for just over half of the cost of the project.

Current Project Status:


Cedar Creek Trunk-Winterset Woods & Sterling Hills

Last Updated

08/12/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

Feb 01, 2014 - Aug 01, 2014

Project Status

Future

Projected Funding:

$565,000

Project Description:

This sanitary sewer improvement project consists of the construction of 2,600 LF of sanitary sewer relief lines ranging in pipe size from 12-inches to 15-inches in diameter on the lower segments of the Cedar Creek Interceptor Subbasins CC-03 and CC-04.

Project Rationale:

The existing lines do not have capacity to convey the predicted peak wet weather sanitary sewer flows nor meet the future needs of development. The condition of the existing pipe system is also a concern. There has been at least one documented overflow in these subbasins.

Current Project Status:


Chipman Road, View High Dr to Bent Tree Dr

Last Updated

12/29/2011

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Apr 01, 2013 - Jun 30, 2014

Project Status

Future

Projected Funding:

$10,414,000

Project Description:

This project is one of six projects funded by the 2007 1/2 cent sales tax renewal. This project will reconstruct the roadway as a 3-lane facility and acquire right-of-way for ultimate divided 4-lane facility with turn lanes. The existing one-lane RR tunnel will be removed, and widened to support two-way traffic. The project will not be constructed until the Union Pacific right-of-way is acquired by the city.

Project Rationale:

SAFETY: This project will improve safety by leveling the roadway and improving sight distance. The right of way component will preserve right of way for future capacity improvements.

Current Project Status:

Wilson and Company of Kansas City, MO began the conceptual study, design and survey work in July 2010. The Concept Phase studied the costs and impacts of several horizontal and vertical alignments. The Concept Phase Alignment report and Traffic Study were completed in January 2011. A public meeting was held on February 8 and the alignment options that were investigated were presented as well as the recommended alignment. The preliminary design began in May, 2011. Wilson completed preliminary design in October, 2011 and is workin gon the right-of-way plans, tract amps and legal descriptions. Land acquisition for easements and right-of-way will begin in February, 2012.


Earthwork for Runway 18-36 Extension and Parallel

Last Updated

12/29/2011

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

May 01, 2012 - Nov 30, 2012

Project Status

Annual Program

Projected Funding:

$8,317,000,000

Project Description:

In accordance with the City Council adopted Airport Business Plan, this project includes the earthwork for the 100 foot wide extension of the existing Runway 18-36 from 4,014 feet to 5,300 feet and for the extension of the west parallel taxiway.

Project Rationale:

Extension of the runway will allow operations of a greater variety of business class aircraft under a greater range of weather conditions. This project will serve to improve the airport and allow more corporate jets to use the facility. These improvements should increase the economic value of the airport to the city. In addition the existing west parallel taxiway is located at 225 feet from Runway 18-36, which is less than the standard separation for a Class C airport. The taxiway is to be relocated to 400 feet from Runway i8-36, which meets the Class C standard.

Current Project Status:

Crawford, Murphy and Tilly (CMT) began the design in May, 2011. Application for environmental permits have been submitted. The design is approximately 60% copmplete and construction can begin in Spring of 2012 if the FAA Grants are in place to fund the project.


Fire Station No. 2 Replacement

Last Updated

10/08/2010

Project Manager(s):

Steve Aldridge
816-969-1205

Estimated Construction Dates:

Aug 09, 2010 - Jun 05, 2011

Project Status

In Construction

Projected Funding:

$8,317,000,000

Project Description:

The new Fire Station 2 consists of approximately 4600 sq. ft. of living/office space and approx 4,500 sq. ft. of apparatus bays. All work is considered traditional construction with no special systems or equipment. The 1.28 acre site is located at 2000 NE Rice Road, near the intersection of NE Rice Road and Colbern Road.

Project Rationale:

Fire Station No. 2 is currently located at 1101 NE Colbern Road, approximately 1/4 mile from the new location. It is a small building on a small site, which does not allow for drive through manuvering for the fire apparatus. In 2007, voters approved the no tax increase general obligation bonds for funding multiple capital improvement projects, including the new fire station.

Current Project Status:

Site grading is 75% complete. Underground utility installation is 50% complete. Foundations and floor slab construction is 100% complete. Exterior and interior concrete masonry walls are 65% complete. Steel stud wall installation is 30% complete.


Hook Road: Ward Rd to Route 291

Last Updated

07/27/2011

Project Manager(s):

George Binger
816-969-1828

Estimated Construction Dates:

Mar 01, 2012 - Nov 01, 2012

Project Status

In Design

Projected Funding:

$7,908,000

Project Description:

This project will widen and reconstruct Hook Road from Ward Road to Hwy. 291. Proposed improvements are to each lane to 12 feet, add paved shoulders and improve drainage pipes/culverts under the road.

Project Rationale:

This project is one of six projects funded by the 2007 1/2 cent sales tax.

Current Project Status:

Project design and concept development is underway. The work is being performed in-house by City staff. The land survey has been completed. Conceptual design work has been completed. Staff will continue to work on design through the end of 2011 and plan for right of way acquistion to take place in 2012.


Jefferson Street Water - Market to Stuart Road

Last Updated

08/15/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

-

Project Status

Future

Project Description:

This rehabilitation project includes the replacement of existing 2-inch galvanized and 4-inch cast-iron water lines with new 8-inch diameter ductile iron lines along Jefferson. The project is funded by the Water Construction fund.

Project Rationale:

The existing lines have a long maintenance history of numerous repairs.

Current Project Status:

This is a future project.


Jefferson Street, Stuart Rd to Persels Rd

Last Updated

02/03/2012

Project Manager(s):

George Binger
816-969-1828

Estimated Construction Dates:

Apr 01, 2014 - Jul 01, 2015

Project Status

Future

Projected Funding:

$9,714,000

Project Description:

Widen and reconstruct Jefferson Street as a 3-lane road from Scherer to Persels. The road will be two lanes from Stuart to Scherer.

Project Rationale:

This project is one of six projects funded by the 1/2 cent sales tax, approved in 2007. Main purpose is to improve safety and flow of traffic along this road.

Current Project Status:

Design estimated to start in 2012, right of way acquistion in 2013 and construction following around 2014-15.


KC Water Supply Proposal - Phase III

Last Updated

08/15/2011

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

-

Project Status

In Construction

Projected Funding:

$7,867,000

Project Description:

Kansas City, Missouri Water Services Department will construct 36,000' of water transmission piping from the East Bottoms Pump Station to Stadium Drive and I-435 to provide additional supply to Lee's Summit. Notification to Kansas City to begin the project was sent in January 2003.

Project Rationale:

Increases water supply from KC to Lee's Summit by 6 MGD to serve future customers.

Current Project Status:

The contractor has started to work on the remaining main.


Lee's Summit Road Lift Station EFHB

Last Updated

08/15/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

May 09, 2012 - Nov 09, 2012

Project Status

In Design

Projected Funding:

$150,000

Project Description:

This project involves rehabilitation of the excess flow holding basin at the Lee's Summit Road Lift Station. The initial project will be a study to recommend appropriate rehab measures. The project budget will be finalized once the study is complete.

Project Rationale:

The concrete-lined basin leaks and fills with groundwater, representing a source of I&I into the sanitary sewer system.

Current Project Status:


Lee's Summit Road, Colbern Rd to city limits

Last Updated

02/01/2012

Project Manager(s):

George Binger
816-969-1828

Estimated Construction Dates:

Mar 01, 2014 - Oct 01, 2015

Project Status

In Design

Projected Funding:

$14,195,000

Project Description:

This project is one of six projects funded by the 1/2 cent sales tax approved in 2007. Lee's Summit is participating on this project as a joint venture with Kansas City, MO and Jackson County. The project will consist of building a 3-lane road with turn lanes. The work will include paved shoulders, multi-use path, street lighting and utility relocation. Lee's Summit will manage design and construction from Colbern Road to Strother Road. Funding will be shared between Lee's Summit and Kansas City with each city paying for the portion within their city limits. There has also been federal funding approved for this project.

Project Rationale:

Primary purpose is safety improvements. Lee's Summit Road is heavily traveled minor arterial, but has several alignment and safety issues. This project will improve safety and expand capacity along this road.

Current Project Status:

Conceptual design, field survey work and traffic studies have been completed. Preliminary Design Work will begin in 2012, along with permitting and development of right of way plans through the end of 2012. Right of way acquisition is planned to start in early 2013 and extend through the end of the year. Construction should start in spring 2014 and be completed in 2015.


North Prairie Lee Lake Sewer System

Last Updated

01/09/2012

Project Manager(s):

David Wahl
816-969-1856

Estimated Construction Dates:

Oct 24, 2011 - Apr 30, 2012

Project Status

In Construction

Projected Funding:

$406,000

Project Description:

This project involves a low pressure sewer system to serve unsewered areas around Prairie Lee Lake as a collaborative project with the residents of this community. The north phase of the project consists of approximately 4,600 feet of small diameter forcemain as the collection system. The residents served by the system will need to establish an improvement district to fund, maintain, and operate the improvements.

Project Rationale:

This project serves existing residents by providing a collection system to replace privately-owned and maintained septic systems.

Current Project Status:

The plans and specifications were revised and combined with the South Prairie Lee Lake Sewer System. Please refer to the South Prairie Lee Lake Sewer System for progress updates.


Scruggs Rd Pump Station Excess Flow Holding Basin

Last Updated

08/15/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

-

Project Status

In Design

Projected Funding:

$1,262,000

Project Description:

This sanitary sewer improvement project consists of the expansion of the existing Excess Flow Holding Basin capacity from 1.4 MG to 4.9 MG.

Project Rationale:

This project will increase the wet weather capacity at the existing basin and reduce the potential of overflows due to future development in the watershed.

Current Project Status:


South Prairie Lee Lake Sewer System

Last Updated

01/09/2012

Project Manager(s):

David Wahl
816-969-1856

Estimated Construction Dates:

Oct 24, 2011 - Apr 30, 2012

Project Status

In Construction

Projected Funding:

$548,000

Project Description:

This project involves a low pressure sewer system to serve unsewered areas around Prairie Lee Lake as a collaborative project with the residents of this community. The south phase of the project consists of approximately 7,700 feet of small diameter forcemain as the collection system. The residents served by the system will need to establish an improvement district to fund, maintain, and operate the improvements.

Project Rationale:

This project serves existing residents by providing a collection system to replace privately-owned and maintained septic systems.

Current Project Status:

The project has been re-combined with the the North system. The plans and specifications for the combined project have been approved by MDNR. The construction contract has been awarded. Construction has started (late-November) on that portion south of Prairie Lee Lake with the main pipe being about half installed. The contractor anticipates activity on the north portion to begin in mid-January while continuing on the south portion. The system will be complete and reayd for residential connection on May 1, 2012.


Strother Road Improvements, Lee's Summit Road to I

Last Updated

02/01/2012

Project Manager(s):

George Binger
816-969-1828

Estimated Construction Dates:

Mar 01, 2013 - Apr 30, 2014

Project Status

In Design

Projected Funding:

$3,675,000

Project Description:

The project includes reconstruction of Strother Road from Lee's Summit Road to Independence Avenue on a new alignment just to the north of the existing road. The road will have a two lanes with paved shoulders.

Project Rationale:

Currently, Strother Road is narrow and substandard in its construction. The proposed reconstruction was identified in the 2006 Thoroughfare Master Plan. The project was approved by voters in the 2010 bond election.

Current Project Status:

City staff is currently working through the preliminary design phase of this project and right-of-way acquisition.


Tudor Road Improvements

Last Updated

05/24/2011

Project Manager(s):

Scott Ward
816-969-1849

Estimated Construction Dates:

Sep 05, 2011 - Apr 05, 2013

Project Status

In Design

Projected Funding:

$11,000

Project Description:

The Tudor Road Improvements project will complete the connection between NW Road Ward and NE Douglas Street. The proposed road will be a divided four lane, built to arterial standards, and have street lights, a sidewalk and a multi-use path. A major component of the project is a bridge over the Union Pacific Railroad. Due to the time required to have the Union Pacific review and approve the bridge over their tracks, the project will be built in two phases. Phase one, from Main to Douglas, is expected to be under construction this fall and completed by winter. Phase two will commence construction upon completion of the agreement with the Union Pacific Railroad, and work on phase two is estimated to begin in the spring of 2012. Depending on construction costs, additional work could include turn lane improvements to the high school and a left turn lane onto NE Woodbury Lane.

Project Rationale:

The Tudor Road Improvements project was approved by voters during the November 2010 no tax increase general obligation bond election. This project will provide another arterial link between Ward Road and Douglas Street and open up approximately 190 acres to development.

Current Project Status:

Council approved the design contract in March 2011. Design work has begun.Construction on the east end of the project could begin as early as fall 2011.


Tudor Road Street Lighting

Last Updated

11/17/2011

Project Manager(s):

Michael Park
816-969-1820

Estimated Construction Dates:

Nov 14, 2011 - Mar 25, 2012

Project Status

In Construction

Projected Funding:

$300,000

Project Description:

Installation of a continuous street lighting on Tudor Road from Douglas Street to M-291 Highway.

Project Rationale:

Currently street lighting on arterial streets is not a part of the leased system. Street lighting provides safety benefits to all road users.

Current Project Status:

The project is under construction.


Ward Road and Persels Road Signal

Last Updated

04/08/2011

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

-

Project Status

In Design

Projected Funding:

$1,186,000

Project Description:

Installation of a traffic signal and geometric turn lanes at Ward Road and Persels Road. Currently, the east and west legs of Persels Road are offset due to the location of the inactive railroad tracks. In order to expedite the design and construction, the project will not utilize federal funding. Federal funding of $700,000 previously allocated for this project was transferred to the Lansgford Road project in FY2005.

Project Rationale:

A traffic study identified this intersection as warranting a traffic signal due to existing traffic volumes. Auxiliary turn lanes will facilitate turning movements and provide better progression through the intersection.

Current Project Status:

Design of the permanent signal is approximately 90 percent complete. Right of way acquisition is complete although permits from the railroad have not been obtained at this time. This project was on hold while the improvements to Longview Road and its intersection with Ward were underway. City staff has also investigated the possible realignment of the east leg of Persels to line up with Persels to the west of Ward. The realignment across the railroad R/W would be a challenge. Discussions are underway between area communities and the Union Pacific RR regarding acquisition of the R/W. Staff is evaluating the possibility of deferring the project until the railroad R/W might be acquired which would provide the opportunity to realign Persels. No decisions has been made at this time. The temporary signal is functioning adequately in the meantime.


Westview School Sanitary Sewer Bank Stabilization

Last Updated

08/15/2011

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

May 09, 2012 - Nov 09, 2012

Project Status

In Design

Projected Funding:

$160,000

Project Description:

This project involves the re-routing of the sewer mains and to abandon approximately 800 lf of main in the stream bank.

Project Rationale:

The re-routing is needed to protect the sewer line from further erosion in the creek bed.

Current Project Status:


Woods Chapel /Gregory Blvd. Street Lighting

Last Updated

11/17/2011

Project Manager(s):

Michael Park
816-969-1820

Estimated Construction Dates:

Nov 14, 2011 - Mar 25, 2012

Project Status

In Construction

Projected Funding:

$355,000

Project Description:

Installation of continuous street lighting along Woods Chapel Road and Gregory Blvd. from the west city limit to Independence Avenue.

Project Rationale:

Currently street lighting on arterial streets is not a part of the leased system. Street lighting provides safety benefits to all road users.

Current Project Status:

The project is under construction.


WPL Watershed - Todd George Rd Pump Station

Last Updated

08/15/2011

Project Manager(s):

Kevin York
816-969-1818

Estimated Construction Dates:

May 09, 2012 - Nov 09, 2012

Project Status

In Design

Projected Funding:

$249,000

Project Description:

This sanitary sewer improvement project consists of the Todd George wet weather pump station to serve a residential area north of the Tudor Road Pump Station.

Project Rationale:

This project maximizes the use of the Tudor Road Pump Station EFHB (1.0 MG) and reduces the risk of sanitary sewer overflows and backups in the Mist subdivision.

Current Project Status: